[edit] Introduction
Lock out tag out (also referred to as lockout/tagout or LOTO) is a safety procedure that protects workers from using machinery that could be dangerous if the power source that operates the equipment is not shut off properly. This practice is also used when machinery needs to be disconnected in order to carry out scheduled maintenance or repair work.
Lock out tag out prevents the machine from being inadvertently restarted while it is in a hazardous state. It also adds a layer of protection for workers who may come into contact with the machine while it is in an unsafe condition.
LOTO is often used when construction workers, electricians, machine operators or other labourers are doing jobs that involve - or are located in close proximity to - equipment that can be hazardous. Failure to control the power supply can result in electrocution, burns, lacerations, amputations and other serious injuries. For example, if LOTO is not used a jammed piece of equipment can suddenly restart, crushing the worker who is trying to clear the jam.
[edit] UK practices
Although this practice is not directly part of UK health and safety regulations, it is recognised as a best practice. Instead of lock out tag out, the UK follows the guidance such as BS 7671, Requirements for Electrical Installations. IET Wiring Regulations. This regulation covers required standards for wiring and electrical installations as well as providing guidance for the proper isolation of electrical equipment.
The operation and maintenance of manufacturing and construction machinery is covered under the Provision and Use of Work Equipment Regulations 1998 (1999 in Northern Ireland) (PUWER). PUWER refers to lock out tag out safety devices, but it does not include guidance as a specific part of the regulation. Instead, PUWER makes a general recommendation akin to lock out tag out practices more closely aligned with those set forward by the Occupational Safety and Health Administration (OSHA) of the United States.
[edit] OSHA practices
The OSHA standard for lock out tag out has been adopted by many international organisations. Standard 1910.147 covers the control of hazardous energy.
According to the OSHA standard, there are three key points about the specific lock out tag out devices:
- They must be identifiable.
- They can only be used for controlling power supply.
- They must be durable, standardised and substantial.
[edit] EU practices
EU 1989/655 guidelines for lock out tag out practices are OSHA based. There is also a specific safety procedure that should be followed when electric equipment is being serviced. This Standard, EN 50110-1, recommends the following five steps:
- Disconnect the equipment completely.
- Secure the machinery so it cannot be reconnected unintentionally.
- Confirm the installation is not operating.
- Perform earthing and short circuiting procedures.
- Protect any live equipment that may be located in close proximity to the equipment being serviced.
[edit] Creating LOTO policy
Lock out tag out policy sets specific safety goals, provides instructions about how to undertake LOTO (by isolation) and explains the benefits and consequences of the policy.
Isolating equipment can include the following procedures:
- Announcing shut off of the equipment.
- Identifying the source(s) of energy.
- Isolating source(s) of energy.
- Locking and tagging sources of energy.
- Proving that the isolation has been successful
Sometimes testing is added to this procedure (referred to as lock tag try or LTT). This takes place when there is an attempt to turn the equipment back on once the isolation step is complete.
It is important to coordinate all lock out tag out plans in advance and specify the duration of the work along with the equipment that will be isolated. It may also be necessary to mark work zones where the isolation will take place to minimise the risk of slip fall occurrences and to prevent access in hazardous areas.
[edit] Related articles on Designing Buildings
- Amendment 3 BS 7671 Requirements for Electrical Installations IET Wiring Regulations.
- Construction health risks.
- Electrical safety.
- Forklift truck.
- Health and safety.
- Health and Safety Executive.
- Health and safety policy.
- Occupational Safety and Health Administration OSHA.
- Safe isolation for low voltage.
[edit] External resources
- BSI, BS 7671:2018+A1:2020 Requirements for Electrical Installations. IET Wiring Regulations
- BS EN 50110-1:2013 Operation of electrical installations. General requirements.
- Legislation.gov.uk, Council Directive of 30 November 1989 concerning the minimum safety and health requirements for the use of work equipment by workers at work (second individual Directive within the meaning of Article 16 (1) of Directive 89/391/EEC) (89/655/EEC) (repealed).
- Legislation.gov.uk, The Provision and Use of Work Equipment Regulations 1998.
- OSHA, Control of Hazardous Energy (Lockout/Tagout).
- OSHA, Standard 1910.147: The control of hazardous energy (lockout/tagout).
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
From project managers to rising stars, sustainability pioneers and more.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.